Planning register

Building Control Application: 22/00291/IN

Skip to tab headings. Skip to tab content.

Reference Number
22/00291/IN
Application Type
Initial Notice
Status
Initial Notice Accepted
Parish
Bicester
Building Surveyor
David Tite
Email
david.tite@cherwell-dc.gov.uk
Phone
07511 047527
Site Address
Proposed Himley Village North West Bicester Middleton Stoney Road Bicester
Description of Works
950 residential unit(s)
Received Date
07/03/2022
Valid Date
09/03/2022
5 Week Date
13/04/2022
8 Week Date
04/05/2022
Decision
Decision Date
Commencement Date
Completion Date
Applicant
Countryside Partnerships South Midlands
Applicant's Address
A Division of Countryside Properties (UK) Ltd The Drive Great Warley Brentwood Essex, CM13 3AT
Agent
NHBC Building Control Services Ltd
Agent's Address
NHBC House Davy Avenue Knowlhill Milton Keynes MK5 8FP
Approved Inspector's Insurer
The Griffiths & Armour Scheme
Competent Persons Scheme Name
N/A
Plot Address Plot Status Commencement Date Completion Date

Planning Applications

Application number Valid Date Application Type Location Proposal Decision Decision Issued Date
14/02121/OUT 31/12/2014 Outline Application Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Oxfordshire OUTLINE - Development to provide up to 1,700 residential dwellings (Class C3), a retirement village (Class C2), flexible commercial floorspace (Classes A1, A2, A3, A4, A5, B1, C1 and D1), social and community facilities (Class D1), land to accommodate one energy centre and land to accommodate one new primary school (up to 2FE) (Class D1). Such development to include provision of strategic landscape, provision of new vehicular, cycle and pedestrian access routes, infrastructure and other operations (including demolition of farm buildings on Middleton Stoney Road) Permitted 30/01/2020
14/00102/SO 31/12/2014 Screening Opinion Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Oxfordshire Development to provide up to 1,700 residential dwellings (Class C3), a retirement village (Class C2), flexible commercial floorspace (Classes A1, A2, A3, A4, A5, B1 and C1), social and community facilities (Class D1), land to accommodate one energy centre and land to accommodate one new primary school (up to 2FE) (Class D1). Such development to include provision of strategic landscape, provision of new vehicular, cycle and pedestrian access routes, infrastructure and other operations (including demolition of farm buildings on Middleton Stoney Road) Screening Opinion requesting EIA 31/12/2014
21/02229/OBL 23/06/2021 Obligation Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Discharge of Schedule 3 Clause 1.1 (exact location and boundaries for Pitch Area 1), Schedule 7 Clause 8.1 (location of the Health Facility Site), Schedule 9 Clause 1.1 and 1.3 (Framework Affordable Housing Scheme and Phase Affordable Housing Scheme), Schedule 11 Clauses 1.1 and 1.3 (Zero Carbon Implementation Strategy), Schedule 12 Clause 1.1 (cultural wellbeing strategy) and Schedule 14 clause 3.1 (location of the allotment land and the phases of the development this fits within), 3.8 (Green Space Framework), 3.10 (Phase Green Space Scheme) and 3.14 (Phase Play Area Scheme) of the S106 Agreement attached to the outline permission 14/02121/OUT Application Withdrawn 03/11/2022
21/02337/DISC 05/07/2021 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Oxfordshire Discharge of condition 7 (phasing plan) 8 (site wide Masterplan and Design Code) 10 (Bio Diversity Strategy) 11 (full surface water drainage scheme) 12 (Built for Life scheme) 13 (future climate impacts statement) 14 (elevated levels of noise) 16 (means of vehicular accesses) 17 (means of footway and cycleway links) 18 (Travel Plan) 19 (detailed surface water drainage scheme) 20 (carbon emissions report) 21 (potential contaminative uses) 22 (comprehensive intrusive investigation) 24 (pollution prevention scheme) 25 (ecological survey) 26 (hedgerows) 27 (Arboricultural Method Statement (AMS)) 28 (Great Crested Newt mitigation strategy) 29 (Landscape & Habitat Management Plan) 30 (Construction Method Statement) 31 (Soil Resources Plan) 32 (archaeological Written Scheme of Investigation) 33 (programme of archaeological evaluation) 34 (foul drainage strategy) 36 (water neutrality strategy) and 37 (Site Waste Management Plan) of 14/02121/OUT Application Withdrawn 03/11/2022
21/02339/REM 22/07/2021 Matters Arising From Outline Approval Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Reserved Matters application for 14/02121/OUT, Phase 1 Development of 500 dwellings, landscaping, new vehicular, cycle and pedestrian access routes and other operations Application Withdrawn 03/11/2022
21/02387/M106 09/07/2021 Application to Modify a Section 106 Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Modification of Section 106 (14/02121/OUT) to amend the mortgagee exclusion clause in Schedule 9, deletion of definition of chargee and to exclude the RP's Lender and the RP itself from liability for the estate wide contributions and obligations Application Withdrawn 03/11/2022
22/01990/CCE 04/07/2022 Compliance with Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Confirmation of Compliance of discharge conditions 2 (expiration date) of 14/02121/OUT Agreed 02/09/2022
22/02375/NMA 05/08/2022 Non Material Amendments Proposed Himley Village North West Bicester Middleton Stoney Road Bicester To change the wording of Conditions 7-11 of application reference 14/02121/OUT to include 'Prior to or alongside the submission of the first application for approval of reserved matters' in place of the words 'Prior to the submission of the first reserved matters' on each of the noted conditions and update to the relevant condition title. (Proposed as non-material amendment to 14/02121/OUT) Permitted 02/09/2022
22/03492/NMA 21/11/2022 Non Material Amendments Proposed Himley Village North West Bicester Middleton Stoney Road Bicester To change the wording of Conditions 2, 4, 7, 8, 9, 10, 11, 13, 14, 18 and 36 :- - Remove the requirement for the first phase RM application to be a "Residential" RM (Condition 2) - To tie commencement of development to the first phase of the development rather than the first "Residential" phase (condition 4) - Change the timing of the submission of details required to discharge conditions 7, 8, 9, 10, 11, 13, 14, 18 and 36 - To allow subsequent variations to any approved Phasing Plan to be submitted to and approved by the LPA (Condition 7) (proposed as non-material amendment to 14/02121/OUT) Permitted 19/12/2022
23/00170/REM 23/01/2023 Matters Arising From Outline Approval Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Reserved Matters Application pursuant to outline planning permission 14/02121/OUT for Phase 1A (infrastructure comprising two junctions to provide vehicular and pedestrian access into the site from Middleton Stoney Road and two initial sections of internal road) along with the partial compliance of conditions 12 (Building for Life 12), 16 (means of vehicular access), 17 (means of pedestrian/cycle links) and 19 (detailed surface water drainage scheme) for Phase 1A. Permitted 27/02/2024
23/00214/REM 24/01/2023 Matters Arising From Outline Approval Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Reserved Matters Application pursuant to outline planning permission 14/02121/OUT for Phase 1A (infrastructure comprising two junctions to provide vehicular and pedestrian access into the site from Middleton Stoney Road and two initial sections of internal road) along with the partial compliance of conditions 12 (Building for Life 12), 16 (means of vehicular access), 17 (means of pedestrian/cycle links) and 19 (detailed surface water drainage scheme) for Phase 1A. Permitted 27/02/2024
23/00183/DISC 23/01/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL DISCHARGE of Condition 20 (Carbon Emissions) and Condition 30 (CEMP) of 14/02121/OUT for Phase 1 only (accesses from Middleton Stoney Road)
23/00207/DISC 24/01/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Discharge of Conditions 7 (site wide Phasing Plan), 11 (full surface Water Drainage Scheme) and 10 (Site Wide Biodiversity Strategy) of 14/02121/OUT (as amended by 22/03492/NMA) Permitted 21/02/2024
23/00781/DISC 22/03/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL DISCHARGE of Condition 32 (Written Scheme of Investigation) of 14/02121/OUT for Phases 1, 2 and a small part of Phase 3 as per Phasing Plan P22-3093_DE_5_B_1 Permitted 19/05/2023
23/01493/REM 07/06/2023 Matters Arising From Outline Approval Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Reserved Matters Application including access, layout, landscaping and scale pursuant to outline planning permission 14/02121/OUT for internal primary and secondary streets along with the partial discharge of conditions 12 (Building for Life 12), 16 (means of vehicular access), 17 (means of pedestrian/cycle links) and 19 (detailed surface water drainage scheme) for Phase 1B
23/01496/DISC 02/06/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Discharge of Condition 8 (Site Wide Masterplan and Design Code) of 14/02121/OUT
23/01502/DISC 02/06/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL DISCHARGE of Condition 20 (Carbon Emissions) of 14/02121/OUT - Phase 2
23/01558/DISC 08/06/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Discharge of Condition 9 (other uses area masterplan) of 14/02121/OUT
23/01586/REM 16/06/2023 Matters Arising From Outline Approval Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Reserved Matters Application pursuant to Outline planning permission 14/02121/OUT for the erection of 123 dwellings (including 37 affordable dwellings), parking, landscaping and other associated infrastructure including the part compliance of conditions 12 (Building for Life 12), 13 (future climate risks statement), 14 (noise assessment), 16 (means of vehicular access), 17 (means of pedestrian/cycle links), 18 (Travel Plan) and 19 (detailed surface water drainage scheme) at Phase 2A
23/01608/DISC 13/06/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL DISCHARGE of Conditions 13 (Future Climate Change Risks Statement) and 36 (Water Neutrality Statement) of 14/02121/OUT (as amended by 22/03492/NMA) for Phase 2
23/02029/DISC 24/07/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL Discharge of Condition 27 (Arboricultural Method Statement) for Phase 1A (accesses) of 14/02121/OUT Permitted 26/10/2023
23/02786/OBL 09/10/2023 Obligation Proposed Himley Village North West Bicester Middleton Stoney Road Bicester Submission of a Zero Carbon Strategy in accordance with paragraph 1.1 of Schedule 11 of the Section 106 agreement dated 30th January 2020 relating to planning permission 14/02121/OUT
23/03546/DISC 19/12/2023 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL Discharge of Condition 29 (Landscape and Habitat Management Plan) of 14/02121/OUT (Phase 2A Only)
24/00615/DISC 05/03/2024 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL Discharge of Condition 30 (Construction Environmental Management Plan) of 14/02121/OUT (Phase 2 only)
24/01036/DISC 17/04/2024 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL DISCHARGE of Condition 21 (Contamination Desk Study) of 14/02121/OUT (PART of Phases 1 and 2 only)
24/01041/DISC 17/04/2024 Discharge Of Conditions Proposed Himley Village North West Bicester Middleton Stoney Road Bicester PARTIAL DISCHARGE of Condition 22 (Contamination - Intrusive Investigation) of 14/02121/OUT (PART Phases 1 and 2 only)

Building Control Applications

Application number Received Date Validated Date Application Type Location Proposal
22/00291/IN 09/03/2022 Initial Notice Proposed Himley Village North West Bicester Middleton Stoney Road Bicester 950 residential unit(s)

Back to top.