Back to results
New search
Reference Number 24/00587/FP
|
Application Type Full Plans
|
Status Building Work Completed
|
Parish |
Building Surveyor David Brown
|
Email david.brown@cherwell-dc.gov.uk
|
Phone 07973 766915
|
Site Address Axis J9 Phase 3
Empire Road
Bicester
|
||
Description of Works
Construction of 5 commercial units.
|
||
Received Date 11/06/2024
|
Valid Date 11/06/2024
|
|
5 Week Date
16/07/2024
|
8 Week Date
06/08/2024
|
|
Decision
Full Plans Conditional Approval
|
Decision Date |
|
Commencement Date
30/07/2024
|
Completion Date
28/02/2025
|
Applicant
Parkway Construction Mk l
|
|
Applicant's Address
5 Newton Court
Knowhill
Milton Keynes
MK5 8NH
|
|
Agent
N/A
|
|
Agent's Address
N/A
|
|
Approved Inspector's Insurer |
Competent Persons Scheme Name
N/A
|
Plot Address | Plot Status | Commencement Date | Completion Date |
---|---|---|---|
Work Complete | 30/07/2024 | 28/02/2025 | |
Work Complete | 30/07/2024 | 28/02/2025 | |
Work Complete | 30/07/2024 | 28/02/2025 | |
Work Complete | 14/10/2024 | 28/02/2025 | |
Work Complete | 14/10/2024 | 28/02/2025 |
Planning Applications | ||||||
Application number | Valid Date | Application Type | Location | Proposal | Decision | Decision Issued Date |
---|---|---|---|---|---|---|
21/03177/F | 30/09/2021 | Full Development | Axis J9 Phase 3 Howes Lane Bicester | Full planning application for employment development (Use Classes E(g)(iii), B2 and/or B8) comprising 5 units within 3 buildings and associated parking and servicing, landscaping and associated works | Appeal Allowed (Against Refusal) | 15/07/2022 |
23/01029/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 4 - (Construction Method Statement) of 21/03177/F | Permitted | 27/07/2023 |
23/01040/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 5 (Construction Environmental Management Plan) of 21/03177/F | Permitted | 15/08/2023 |
23/01031/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of condition 6 (segregated pedestrian and cycle path) of 21/03177/F | Permitted | 27/07/2023 |
23/01032/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 7 (access details) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 02/02/2024 |
23/01033/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 9 - (route of service connections) of 21/03177/F | Permitted | 19/02/2024 |
23/01034/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Partial discharge of Condition 10 (BREEAM ‘Very Good’) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 07/07/2023 |
23/01035/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 26 - (acoustic fences) of 21/03177/F | Permitted | 30/06/2023 |
23/01038/DISC | 19/04/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 32 (Framework Travel Plan) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 27/10/2023 |
23/01205/NMA | 04/05/2023 | Non Material Amendments | Axis J9 Phase 3 Howes Lane Bicester | Vary the list of approved plans set out in Condition 2 to alter Unit 4’s loading door arrangements to accommodate the operations of tenants (proposed as non-material amendment to 21/03177/F) | Permitted | 01/06/2023 |
23/01271/DISC | 11/05/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 11 (details of visibility splays) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 30/06/2023 |
23/01800/OBL | 29/06/2023 | Obligation | Axis J9 Phase 3 Howes Lane Bicester | Training and Employment Plan to satisfy the requirements of Schedule 2 of the Section 106 Agreement associated with planning permission ref 21/03177/F | Permitted | 16/02/2024 |
23/01857/DISC | 06/07/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of condition 13 (landscaping) of 21/03177/F | Permitted | 27/11/2023 |
23/01955/NMA | 17/07/2023 | Non Material Amendments | Axis J9 Phase 3 Howes Lane Bicester | Non-material amendment to 21/03177/F - Application to amend the wording of condition 8 to reflect the required Tree Protection and Retention Plan | Permitted | 29/09/2023 |
23/02281/DISC | 16/08/2023 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 20 (Biodiversity enhancement technical note) of 21/03177/F - (APP/C3105/W/22/3304021) | Permitted | 21/12/2023 |
24/00687/NMA | 12/03/2024 | Non Material Amendments | Axis J9 Phase 3 Howes Lane Bicester | Non-material amendment to 21/03177/F - modification to the approved plans | Permitted | 08/04/2024 |
24/01894/DISC | 16/07/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 30 (Real Time Energy Display) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 10/09/2024 |
24/01897/DISC | 16/07/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 22 (boundary enclosures) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 14/11/2024 |
24/01896/DISC | 16/07/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 23 (air source heat pump details) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 28/08/2024 |
24/01895/DISC | 16/07/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 27 (water consumption) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 03/10/2024 |
24/01925/DISC | 17/07/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 28 (mechanical ventilation or extraction equipment) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 10/09/2024 |
24/01954/DISC | 19/07/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of Condition 21 (Landscape Ecology Management Plan) of 21/03177/F (APP/C3105/W/22/3304021) | Permitted | 03/10/2024 |
24/02396/DISC | 04/09/2024 | Discharge Of Conditions | Axis J9 Phase 3 Howes Lane Bicester | Discharge of condition 19 (solar PV) of 21/03177/F | Permitted | 01/11/2024 |
24/02565/NMA | 30/09/2024 | Non Material Amendments | Axis J9 Phase 3 Howes Lane Bicester | Non-material amendment to 21/03177/F - vary the list of approved plans set out in Condition 2. Amendments are also required to conditions 24, 25 and 26 to ensure consistency (by referring to the updated plan, to be referenced at Condition 2). | Permitted | 14/11/2024 |
24/02898/ADV | 11/11/2024 | Advertisement | Cabot Park Empire Road Bicester OX26 2GE | 3 no non illuminated totem signs | Permitted | 14/01/2025 |
Appeal Applications | ||||||
Appeal number | Appeal Start Date | Appeal Type | Location | Proposal | Decision | |
---|---|---|---|---|---|---|
22/00045/REF | 04/10/2022 | Appeal against Refusal | Axis J9 Phase 3 Howes Lane Bicester | Full planning application for employment development (Use Classes E(g)(iii), B2 and/or B8) comprising 5 units within 3 buildings and associated parking and servicing, landscaping and associated works | Appeal Allowed |
Building Control Applications | ||||||
Application number | Received Date | Validated Date | Application Type | Location | Proposal | |
---|---|---|---|---|---|---|
24/00587/FP | 11/06/2024 | 11/06/2024 | Full Plans | Axis J9 Phase 3 Empire Road Bicester | Construction of 5 commercial units. |