Reference Number 22/00445/FP
|
Application Type Full Plans
|
|
Status Full Plans Conditional Approval
|
Parish Hook Norton
|
|
Building Surveyor Donald McAllister
|
Email donald.mcallister@cherwell-dc.gov.uk
|
Phone 07974 326811
|
|
Site Address Hook Norton Baptist Church
Netting Street
Hook Norton
OX15 5NJ
|
||
|
Description of Works
Refurbishment of the chapel (new floor, attic insulation, new hating, lighting, ventilation, fire escapes etc.
|
||
|
Received Date 12/04/2022
|
Valid Date 25/05/2022
|
|
|
5 Week Date
29/06/2022
|
8 Week Date
20/07/2022
|
|
|
Decision
Full Plans Conditional Approval
|
Decision Date
27/05/2022
|
|
|
Commencement Date
29/01/2024
|
Completion Date |
|
|
Applicant
Pastor Peter Brookes
|
|
|
Applicant's Address
Hook Norton Baptist Church
Netting Street
Hook Norton
OX15 5NJ
|
|
|
Agent
Mr Peter Preston
|
|
|
Agent's Address
3 Thames Street
Eynsham
Witney
OX29 4HF
|
|
|
Approved Inspector's Insurer |
Competent Persons Scheme Name
N/A
|
| Plot Address | Plot Status | Commencement Date | Completion Date |
|---|---|---|---|
| Work Commenced | 29/01/2024 |
Planning Applications | ||||||
| Application number | Valid Date | Application Type | Location | Proposal | Decision | Decision Issued Date |
|---|---|---|---|---|---|---|
| 04/00615/TCA | 17/03/2004 | Works To Trees In Conservation Area | Baptist Church Netting Street Hook Norton Banbury Oxon | Fell 1 No. Spruce tree | Permitted | 28/04/2004 |
| 06/00299/F | 17/02/2006 | Full Development | Baptist Church Netting Street Hook Norton Banbury Oxon | Proposed drop off point/car park | Application Withdrawn | 19/04/2006 |
| 06/01091/F | 01/06/2006 | Full Development | Baptist Church Netting Street Hook Norton Oxfordshire | Resubmission of 06/00299/F - Proposed drop off point/car park | Permitted | 27/07/2006 |
| 11/00122/F | 28/01/2011 | Full Development | Hook Norton Baptist Church Netting Street Hook Norton Banbury Oxfordshire OX15 5NJ | Installation of Solar PV Panels on south facing roof | Permitted | 23/03/2011 |
| 11/00123/LB | 28/01/2011 | Listed Building | Hook Norton Baptist Church Netting Street Hook Norton Banbury Oxfordshire OX15 5NJ | Installation of Solar PV Panels on south facing roof | Permitted | 23/03/2011 |
| 16/00274/TCA | 05/10/2016 | Works To Trees In Conservation Area | Hook Norton Baptist Church Netting Street Hook Norton Banbury OX15 5NJ | T1 x Oak - Crown clean removing deadwood and thin by 15% T2 x T3 x Yew - Crown raise to 4.5m and remove lower poor pruning cuts | Permitted | 11/11/2016 |
| 18/01931/MISC | 08/11/2018 | Miscellaneous Enquiries | Hook Norton Baptist Church Netting Street Hook Norton Banbury OX15 5NJ | The complete refurbishment of the chapel to create a warm, comfortable and welcoming space fit for use in the 21st century. The project will be split into at least three phases with the first phase aimed at addressing the majority of the fabric issues raised by the recent Quinquennial Inspection. As such, Phase 1 is mostly external works focussing on storm water drainage, re-pointing, installation of a new fire door to the vestry, replacement of internal fire doors, new external security doors to the porch, installation of external access ramp, installation of thermal insulation to the roof space and boarding of roof space to enable storage. Phase 2 focuses on the replacement of the decayed suspended timber floor with a breathable and insulated limecrete floor, the removal of the Victorian side galleries and the replacement of the heating, lighting, power and AV systems. The final phase, Phase 3, involves the repair and refurbishment of the Georgian rear balcony with new pews and other minor internal works. | No Objections | 25/01/2019 |
| 21/03676/F | 28/10/2021 | Full Development | Hook Norton Baptist Church Netting Street Hook Norton OX15 5NJ | Demolition of redundant post war boiler shed to rear elevation. Introduction of new doors to archway of porch. Opening up and widening of former door opening to vestry to form fire escape. Replacement of existing uneven paths with self binding gravel suitable for wheelchair access. New below ground drainage. | Permitted | 04/02/2022 |
| 22/01697/TCA | 24/05/2022 | Works To Trees In Conservation Area | Hook Norton Baptist Church Netting Street Hook Norton OX15 5NJ | T1 x Norway Spruce. Fell poor specimen previously topped and formed week union and below. | Permitted | 01/07/2022 |
| 23/03314/DISC | 27/11/2023 | Discharge Of Conditions | Hook Norton Baptist Church Netting Street Hook Norton Oxfordshire OX15 5NJ | Discharge of Condition 3 (Arboricultural Method Statement) of 21/03676/F | Permitted | 22/01/2024 |
| 26/00151/TCA | 21/01/2026 | Works To Trees In Conservation Area | Hook Norton Baptist Church Netting Street Hook Norton Banbury OX15 5NJ | T1x Yew Crown- Crown raise over neighbouring property by approx 4m. By removal first four lower laterals. T2 x Holly Removal of 2 stems close to building. | ||
Building Control Applications | ||||||
| Application number | Received Date | Validated Date | Application Type | Location | Proposal | |
|---|---|---|---|---|---|---|
| 22/00445/FP | 12/04/2022 | 25/05/2022 | Full Plans | Hook Norton Baptist Church Netting Street Hook Norton OX15 5NJ | Refurbishment of the chapel (new floor, attic insulation, new hating, lighting, ventilation, fire escapes etc. | |