Planning register

Building Control Application: 21/00335/FP

Skip to tab headings. Skip to tab content.

Reference Number
21/00335/FP
Application Type
Full Plans
Status
Full Plans Approval
Parish
Launton
Building Surveyor
Donald McAllister
Email
donald.mcallister@cherwell-dc.gov.uk
Phone
07974 326811
Site Address
Wits End The Green Launton Bicester OX26 5EF
Description of Works
Proposed Ground and First floor extension with associated works to create a new utility and kitchen area with an enlarged bedroom and ensuite over.
Received Date
18/03/2021
Valid Date
23/03/2021
5 Week Date
27/04/2021
8 Week Date
18/05/2021
Decision
Full Plans Approval
Decision Date
26/03/2021
Commencement Date
03/08/2021
Completion Date
Applicant
Mark Walton
Applicant's Address
Wits End The Green Launton Bicester OX26 5EF
Agent
N/A
Agent's Address
N/A
Approved Inspector's Insurer
Competent Persons Scheme Name
N/A
Plot Address Plot Status Commencement Date Completion Date
Work Commenced 03/08/2021

Planning Applications

Application number Valid Date Application Type Location Proposal Decision Decision Issued Date
20/02794/F 07/10/2020 Full Development Wits End The Green Launton OX26 5EF Create new gable end on garage to raise roof line; extension to the rear to increase size of kitchen Refused 02/12/2020
20/03709/F 29/12/2020 Full Development Wits End The Green Launton OX26 5EF Raise the garage roof line; extension to the rear to increase the size of the kitchen - re-submission of 20/02794/F Permitted 23/02/2021

Building Control Applications

Application number Received Date Validated Date Application Type Location Proposal
CP/OFTEC/00021/2011 12/06/2010 12/06/2010 Oil Firing Technical Association Wits End The Green Launton Bicester Oxfordshire OX26 5EF Install a domestic oil storage facility External
CP/FENSA/05408/2015 16/05/2011 16/05/2011 Window replacement schemes Wits End The Green Launton Bicester OX26 5EF 14 Windows 2 Doors
21/00335/FP 18/03/2021 23/03/2021 Full Plans Wits End The Green Launton Bicester OX26 5EF Proposed Ground and First floor extension with associated works to create a new utility and kitchen area with an enlarged bedroom and ensuite over.