Description of Works
Phase 2 - 181 dwellings
Received Date
01/06/2018
Valid Date
01/06/2018
5 Week Date
06/07/2018
8 Week Date
27/07/2018
Decision
Full Plans Conditional Approval
Decision Date
13/08/2018
Commencement Date
09/05/2018
Completion Date
Applicant
Bloor Homes Western
Applicant's Address
Western House Furrowfield Park Tewkesbury Gloucestershire DL29 8UR
Agent
N/A
Agent's Address
N/A
Approved Inspector's Insurer
Competent Persons Scheme Name
N/A
Plot Address Plot Status Commencement Date Completion Date
Work Complete 31/05/2018 18/01/2018
Work Complete 20/07/2018 06/11/2018
Work Complete 14/05/2018 06/11/2018
Work Complete 18/05/2018 21/11/2018
Work Complete 09/05/2018 05/12/2018
Work Complete 10/05/2018 05/12/2018
Work Complete 10/05/2018 05/12/2018
Work Complete 24/05/2018 19/12/2018
Work Complete 04/07/2018 06/02/2019
Work Complete 06/07/2018 14/02/2019
Work Complete 20/06/2018 04/03/2019
Work Complete 20/06/2018 04/03/2019
Work Complete 20/06/2018 04/03/2019
Work Complete 20/06/2018 04/03/2019
Work Complete 06/07/2018 04/03/2019
Work Complete 20/06/2018 04/03/2019
Work Complete 27/07/2018 13/03/2019
Work Complete 27/07/2018 13/03/2019
Work Complete 27/07/2018 13/03/2019
Work Complete 20/06/2018 25/03/2019
Work Complete 27/07/2018 25/03/2019
Work Complete 27/07/2018 25/03/2019
Work Complete 27/07/2018 25/03/2019
Work Complete 27/07/2018 25/03/2019
Work Complete 27/07/2018 25/03/2019
Work Complete 25/03/2019
Work Complete 28/03/2019
Work Complete 28/03/2019
Work Complete 28/03/2019
Work Complete 26/04/2019
Work Complete 26/04/2019
Work Complete 03/05/2019
Work Complete 10/05/2019
Work Complete 10/05/2019
Work Complete 10/05/2019
Work Complete 10/05/2019
Work Complete 17/05/2019
Work Complete 05/09/2018 17/05/2019
Work Complete 05/09/2018 17/05/2019
Work Complete 30/05/2019
Work Complete 30/05/2019
Work Complete 18/09/2018 30/05/2019
Work Complete 03/10/2018 06/06/2019
Work Complete 11/07/2019
Work Complete 11/07/2019
Work Complete 11/07/2019
Work Complete 15/07/2019
Work Complete 02/08/2018 01/08/2019
Work Complete 13/08/2018 01/08/2019
Work Complete 02/08/2018 01/08/2019
Work Complete 27/09/2018 09/08/2019
Work Complete 27/09/2018 09/08/2019
Work Complete 09/08/2019
Work Complete 23/08/2019 23/08/2019
Work Complete 23/08/2019 23/08/2019
Work Complete 23/08/2019 23/08/2019
Work Complete 29/08/2019 30/08/2019
Work Complete 06/09/2019 13/09/2019
Work Complete 06/09/2019 13/09/2019
Work Complete 06/09/2019 13/09/2019
Work Complete 09/10/2018 17/09/2019
Work Complete 30/08/2018 17/09/2019
Work Complete 26/06/2019 04/10/2019
Work Complete 26/06/2019 04/10/2019
Work Complete 26/06/2019 04/10/2019
Work Complete 01/11/2019
Work Complete 01/11/2019
Work Complete 01/11/2019
Work Complete 06/11/2019
Work Complete 22/11/2019
Work Complete 22/11/2019
Work Complete 06/12/2018 22/11/2019
Work Complete 29/11/2019
Work Complete 12/12/2019
Work Complete 12/12/2019
Work Complete 20/12/2019
Work Complete 20/12/2019
Work Complete 09/01/2020
Work Complete 10/01/2020
Work Complete 17/01/2020
Work Complete 31/01/2020
Work Complete 28/11/2018 31/01/2020
Work Complete 21/05/2018 03/02/2020
Work Complete 11/06/2018 03/02/2020
Work Complete 09/08/2018 03/02/2020
Work Complete 03/02/2020
Work Complete 03/02/2020
Work Complete 26/06/2019 03/02/2020
Work Complete 03/02/2020
Work Complete 24/05/2018 03/02/2020
Work Complete 26/06/2019 03/02/2020
Work Complete 09/04/2020
Work Complete 14/05/2020
Work Complete 05/06/2020
Work Complete 12/06/2020
Work Complete 17/06/2020
Work Complete 19/06/2020
Work Complete 22/06/2020
Work Complete 13/07/2020
Work Complete 13/07/2020
Work Complete 31/07/2020
Work Complete 31/07/2020
Work Complete 06/08/2020
Work Complete 06/08/2020
Work Complete 04/09/2020
Work Complete 04/09/2020
Work Complete 04/09/2020
Work Complete 04/09/2020
Work Complete 28/11/2018 04/09/2020
Work Complete 11/09/2020
Work Complete 11/09/2020
Work Complete 11/09/2020
Work Complete 25/09/2020
Work Complete 06/10/2020
Work Complete 03/09/2020 08/10/2020
Work Complete 15/01/2020 08/10/2020
Work Complete 15/01/2020 08/10/2020
Work Complete 19/07/2020 08/10/2020
Work Complete 16/10/2020
Work Complete 16/10/2020
Work Complete 23/10/2020
Work Complete 30/10/2020
Work Complete 06/11/2020
Work Complete 26/11/2020
Work Complete 10/12/2020
Work Complete 11/07/2019 10/12/2020
Work Complete 03/02/2021
Work Complete 03/02/2021
Work Complete 03/02/2021
Work Complete 12/02/2021
Work Complete 19/02/2021
Work Complete 24/02/2021
Work Complete 05/03/2021
Work Complete 12/03/2021
Work Complete 19/03/2021
Work Complete 26/03/2021
Work Complete 02/10/2019 31/03/2021
Work Complete 16/04/2021
Work Complete 16/04/2021
Work Complete 23/04/2021
Work Complete 28/04/2021 28/04/2021
Work Complete 21/05/2021
Work Complete 06/10/2020 28/05/2021
Work Complete 18/08/2020 25/06/2021
Work Complete 18/08/2020 25/06/2021
Work Complete 07/07/2021
Work Complete 29/07/2021
Work Complete 29/07/2021
Work Complete 29/07/2021
Work Complete 29/07/2021
Work Complete 29/07/2021
Work Complete 29/07/2021
Work Complete 26/08/2021
Work Complete 26/08/2021
Work Complete 06/09/2021
Work Complete 06/09/2021
Work Complete 06/09/2021
Work Complete 08/09/2021
Work Complete 04/10/2021
Work Complete 08/10/2021
Work Complete 08/10/2021
Work Complete 29/10/2021
Work Complete 29/10/2021
Work Complete 29/10/2021
Work Complete 30/10/2021
Work Complete 30/10/2021
Work Complete 05/11/2021
Work Complete 06/11/2021
Work Complete 13/11/2021
Work Complete 26/11/2021
Work Complete 30/03/2021 26/11/2021
Work Complete 30/03/2021 17/12/2021
Work Complete 25/03/2021 17/12/2021
Work Complete 30/03/2021 17/12/2021
Work Complete 22/03/2021 17/12/2021
Work Complete 23/12/2021
Work Complete 23/12/2021
Work Complete 23/09/2022
Work Complete 23/09/2022
Work Complete 23/09/2022
Work Complete 23/09/2022
Work Complete 23/09/2022

Building Control Applications

Application number Received Date Validated Date Application Type Location Proposal
18/00905/PARTFP 01/06/2018 01/06/2018 Partnership Banbury Rise Land North Of Withycombe Farm West Of Edinburgh Way Banbury Phase 2 - 181 dwellings

Back to top.